Sector focus
  The group’s capabilities have been refined to deliver comprehensive infrastructure solutions in sectors with high potential. The next few spreads outline the group’s capabilities in its target sectors.

Water

2008 2009 2010 2011 2012
Green arrow up Green arrow up Green arrow up Green arrow up Green arrow up
Durban harbour entrance widening – South Africa

Durban harbour widening by 100 metres. Removal and replacement of existing northern breakwater, extension of southern breakwater and deepening of harbour entrance by three metres to a depth of 19 metres.

King Shaka International Airport – South Africa

Design and construction of an international airport in KwaZulu-Natal.

Gauteng Freeway Improvement Project – packages A and E – South Africa

Packages included lane additions and improvements to interchanges as part of SANRAL’s freeway improvements

Gauteng Freeway Improvement Project – package E – South Africa

Extensive lane additions and improvements to interchanges as part of SANRAL’s freeway improvements.

  Chota Motala Interchange – South Africa

This contract in KwaZulu-Natal comprises an upgrade of the freeway from a four-lane carriage way to a six-lane free flowing and remodelled interchange. The interchange consisted of two major structures, including the demolition and the reconstruction of the grade separation bridge and an incrementally launched fly-over bridge, as well as all associated works.


Key competencies

arrow Co-developer, equity participant and turnkey design and build contractor in transport concessions
arrow Engineer, procure and construct (EPC) delivery of transport infrastructure
arrow Multi-disciplinary constructor of roads, railways, ports, harbours and airports

Key differentiators

Beige arrow International experience across Africa, the Middle East and Europe
Beige arrow Reputation for timeous and technicallyc complex delivery
Beige arrow Large contract capability
Beige arrow EPC competence

  CASE STUDY
   
  Koeberg interchange – Cape Town

    A critical road upgrade    
The Koeberg interchange carrying more than 200 000 vehicles per day had been operating below acceptable service levels for many years prior to the award of the 2010 FIFA Soccer World Cup. The time pressure to achieve the improvement to both the N1 and the M5 freeways prior to the event required quick action and innovative design from Group Five and its joint venture partner, Power Construction. Alternative technical solutions were proposed during tendering, which contributed to the group securing the contract.

Ramp A was opened on schedule in time for the 2010 FIFA Soccer World Cup and Ramp B was opened to traffic in June 2011, four months ahead of schedule.

The design challenges of threading two new intersecting ramps, each approximately 700 metres long, at a third level above the existing interchange, required the design of elements such as piers and capping beams, to allow repetitive use of formwork and the aesthetically pleasing precast u-beam structures. This allowed maximum off-site production which minimised the build programme and reduced traffic disruption. The contract used the largest pre-cast beams to have ever been constructed in South Africa.

The construction team had to overcome enormous challenges, such as several buried and unrecorded services. This even included a buried old naval oil pipeline still full of oil from the second World War!

An entire riverbed had to be relocated during winter, which required careful hydraulic control and innovative use of labour-intensive gabion baskets.

This contract demonstrates the group’s ability to construct technically complex infrastructure upgrades in a working urban environment through the use of specialist technologies.